Required Residential Inspections

  • FOOTING...........................Continuous keyway
  • FOUNDATION.................... After receipt of foundation as-built by building/inspections dept.  As-built must be uploaded into your permit application through permiteyes. Tar line should reflect frost protection coverage
  • SONOTUBES......................Installed, but prior to concrete placement
  • ROUGH WIRING.................Prior to rough frame inspection and passed
  • ROUGH PLUMBING...........Prior to rough frame inspection and passed
  • ROUGH GAS......................Prior to rough frame inspection and passed
  • ROUGH HVAC....................Along with rough frame inspection
  • ROUGH FRAME.................Rough wiring, plumbing and gas signed off, and all pre-insulation in place (any component of the insulation process that will be concealed).
  • INSULATION......................100% in place in all areas that will be covered by wall board.
  • FINAL WIRING
  • FINAL PLUMBING
  • FINAL GAS
  • FINAL BUILDING...............Only after all applicable sign offs are received.  Hers Rater Certificate must be uploaded to permiteyes and received by the building / inspections department 
  • IT IS THE PERMIT HOLDER'S RESPONSIBILITY TO OBTAIN ALL SIGN OFFS APPLICABLE TO THE BUILDING PERMIT.  PLEASE DO NOT SCHEDULE A FINAL INSPECTION UNTIL ALL SIGN OFFS ARE RECORDED ON THE BUILDING PERMIT CARD.
  • REINSPECTION FEE OF $50.00 MAY BE ASSESSED AS NECESSARY.